On this page, you can check the general preparation guidelines needed for the exhibition. It includes overall information such as exhibitor responsibilities for product protection, booth setup, electricity usage, and dismantling schedules. Please review these details to ensure a smooth exhibition experience๏ผ
1. Exhibit Protection
โข
The Exhibition Secretariat has contracted with a security service provider to offer 24-hour security within the exhibition hall during the exhibition period, as well as during setup and dismantling. However, the final responsibility for the protection and potential loss of exhibits lies with the exhibitors. Exhibitors are advised to take precautions to safeguard any exhibits at risk of damage. Please note that the Exhibition Secretariat is not liable for any damage to exhibits resulting from natural disasters, arson, theft, or vandalism.
2. Application for After-Hours Work
โข
During the setup and dismantling periods, the exhibition hall usage hours are as follows, and exhibitors must strictly adhere to them.
Category | Hall | Usage Hours |
Setup
(Space-Only) | Hall C | March 3 (Mon), 02:00 - 22:00
March 4 (Tue), 07:00 - 22:00 |
Halls A, B, D | March 3 (Mon), 05:00 - 22:00
March 4 (Tue), 07:00 - 22:00 | |
Hall GB | March 3 (Mon), 08:00 - 20:00
March 4 (Tue), 08:00 - 22:00 | |
Move-out and Dismantling | Hall C | March 7 (Move-out): 17:00 - 22:00
March 8 (Dismantling): 08:00 - 18:00 |
Hall A | March 7 (Move-out): 17:30 - 22:00
March 8 (Dismantling): 08:00 - 18:00 | |
Hall D | March 7 (Move-out): 18:00 - 22:00
March 8 (Dismantling): 08:00 - 18:00 | |
Hall B | March 7 (Move-out): 18:30 - 22:00
March 8 (Dismantling): 08:00 - 18:00 | |
Hall GB | March 7 (Same-Day Dismantling): 17:00 - 24:00 | |
Hall Platz, Lobby | March 7 (Same-Day Dismantling): 17:00 - 20:00 |
โป For Hall C, due to a high number of large independent booths and narrow aisles, additional setup hours are provided compared to other halls for safety reasons.
โข
However, if it is unavoidable to use the exhibition hall outside the designated hours, exhibitors must submit an "After-Hours Hall Usage Application" to the on-site Exhibition Secretariat by 16:00 on the same day for security and safety management. Additional costs will apply for after-hours work.
3. Space Only Booth : Exhibitor-Constructed (Direct Selection of Exhibition Contractor)
โข
Provided by the Organizer: Only floor space is provided (1 booth size = 3m x 3m).
โข
Booth Height Limit: Maximum 5m (For large corporate booths along the walls, construction up to 6M is allowed).
โป For swing spaces between Halls A/B or C/D, the maximum height is 4M.
โป For the Grand Ballroom, maximum height is 3m.
โป Exceeding 5M requires structural review approval from a certified agency.
โข
Exhibition setup for space-only booths must be conducted through contractors designated by COEX.
โข
Contractors for space-only booths are prohibited from affixing decorations, signboards, or other items by nailing or tacking to the COEX ceiling, walls, or columns, as this may damage the building.
โข
All booth ceilings must remain open.
โข
Booth structures should be pre-fabricated as much as possible to allow for final touches during setup, and all materials used in booth assembly must be non-combustible or treated with flame retardant.
โข
Carpets for exhibition flooring should be easily removable, and no attachments may be applied to walls, floors, ceilings, or other structural elements of the exhibition hall.
โข
Structures and equipment, including lighting fixtures, must not extend beyond the allocated booth area.
โข
Booth Design Submission
โฆ
Exhibitors with space-only booths must submit the Independent Booth Installation Application and design plans (one copy each of the floor plan and elevation view) to the Hall Manager's Office of the Exhibition Rental Team through their setup contractor.
โฆ
The cover of the submitted design plans must include the booth number, exhibitor name, and design company.
โข
Rigging (Hoist) Usage
โฆ
Lightweight items, such as banners, may be installed on the ceiling in designated areas (certain sections of Hall A and Hall C) after confirming the location with the InterBattery Secretariat. If approved, an application can then be submitted.
โฆ
Please adhere to the following guidelines during rigging work, and complete both the online application and work notification to COEX:
โช
For point hoist (rigging) work, do not exceed the weight load per point. If necessary, submit a structural calculation report related to point hoist (rigging) installation with the work notification to COEX.
โช
The truss material used for the point hoist (rigging) must be made of aluminum alloy.
โช
When attaching accessories, such as lights or moving lights, to the truss, secure them with an additional safety ring along with fixed bolts for double safety.
โช
During point hoist (rigging) work, no other setup work should take place within the working radius below. A safety officer (on-site representative) must be present to provide safety guidance.
โช
Electrical work required for operating trusses and other structures must be carried out by an electrical contractor registered with COEX.
โข
Double-Decker Structures
โฆ
For double-decker installations, the contractor must submit a detailed structural calculation report addressing safety to COEX at least two weeks prior to the exhibition. After construction is completed, an on-site inspection report must be submitted before the event begins.
โฆ
If you are planning a double-decker structure, please contact the Secretariat to review the necessary guidelines.
โข
CAD Floorplan(Hall A-C) for booth with pillars
4. Shell Scheme Booths: Installation and Dismantling Managed by the Organizer
โข
Shell Scheme Booth Inclusions
โฆ
Booth walls (3m x 3m x 2.5m), company name sign (in both Korean and English), booth number, five spotlights (100W), basic electricity supply (220V, 1kW), one power outlet, flooring (Pytex), one set of information desk and chair
Item | Quantity Provided | Notes |
Booth Wall Panels | 9 panels for one-side open booth | |
6 panels for two-side open booth | ||
Main Banner (2.9m x 0.8m) | 1 | In both Korean and English |
Spotlight (100W) | 5 | 3 inside booth |
2 for main banner | ||
Power Outlet (220V, single-phase, double socket) | 1 | |
Flooring (Pytex) | 3m x 3m | |
Information Desk/Chair | 1 each |
โป For specifications and materials related to shell scheme booths, please contact the designated booth installation contractor.
โข
One information desk and one chair are provided per exhibitor, regardless of booth size.
โฆ
Electricity is not provided for purposes other than lighting. If additional power is required for equipment demonstrations or other uses, a separate application must be submitted.
โข
The company name sign will display text only, in a standardized font. For adding logos or CI images, please confirm feasibility with the shell scheme contractor, as this may incur additional costs.
โข
Logo and CI image files must be in AI format (jpg, png, and gif files are not accepted).
โข
Exhibitorโs Responsibility: Display items and interior decoration.
โป Consultation tables, display stands, etc., can be rented from COEX-designated furniture and equipment rental companies (additional costs apply).
Guidelines
โข
No additional installations outside the basic booth structure are allowed, and exhibitors may not nail or drill holes.
โข
When displaying items on modular panels, use 'S' hooks or wire hooks, which can help prevent damage to the panels and avoid restoration fees.
5. Premium Booths: Installation and Dismantling Managed by the Organizer
โข
Premium exhibit space with high-quality standard fixtures
โข
Size: Width 3m x Depth 3m x Height 3.5m (wall height 2.5m)
โข
Basic Fixtures Provided
Booth | 1 set of wooden paneling and Maxima system, 1 LED name sign |
Furniture | 1 information desk (including folding chair)
Consultation table set (1 round table + 4 chairs) provided for booths with 2 or more units |
Electricity | 5 spotlights, 1 set of 220V double socket outlet |
Flooring | Pytex flooring, 3m x 3m (structure area: 9ใก) |
6. Lobby Booths (Halls B/D, Grand Ballroom): Installation and Dismantling Managed by the Organizer
โข
Premium exhibit space with high-quality standard fixtures
โข
Size
โฆ
B/D Hall Lobby: Width 3m x Depth 3m (wall height 2m) x Total Height 3m (wall height 2.5m)
โฆ
Grand Ballroom Lobby: Width 3m x Depth 2m (wall height 1m) x Total Height 3m (wall height 2.5m)
โข
Basic Fixtures Provided
Booth Structure | 1 set of wooden paneling and Maxima system, 1 LED name sign |
Furniture | 1 information desk (including folding chair) |
Electricity | 2 spotlights, 1 set of 220V double socket outlet |
Flooring (Pytex) | B/D Hall: 3m x 3m = 9ใก
Grand Ballroom: 3m x 2m = 6ใก |
7. Platz Hall Shell Scheme Booth: Installation and Dismantling Managed by the Organizer
โข
Premium exhibit space with high-quality standard fixtures
โข
Size: Width 3m x Depth 2m x Height 2.5m
โข
Basic Fixtures Provided
Booth Structure | 1 set of wooden booth system |
Furniture | 1 stool and chair set |
Electricity | Lighting, 1 set of 220V double socket outlet |
Flooring | Pytex, 3m x 2m = 9ใก |
8. Exhibit Entry Dimensions
โข
Exhibition Hall (Halls A, B, C, D) Cargo Entrance: Width 6m x Height 4m
โข
Exhibition Hall (Grand Ballroom, Platz Hall) Cargo Entrance: Width 1.57m x Height 2.33m
โข
Please check your exhibits in advance to ensure they will not obstruct or get stuck at the cargo entrance.
9. Dismantling Schedule
โข
Exhibit Removal and Booth Dismantling
โฆ
After the exhibition ends, please ensure drawers and shelves are empty when the designated contractor collects furniture. The Secretariat is not responsible for any damage or loss incurred.
โฆ
Hall C
โช
Removal: March 7 (Fri), 17:00 โ 22:00
โช
Dismantling: March 8 (Sat), 08:00 โ 18:00
โฆ
Hall A
โช
Removal: March 7 (Fri), 17:30 โ 22:00
โช
Dismantling: March 8 (Sat), 08:00 โ 18:00
โฆ
Hall D
โช
Removal: March 7 (Fri), 18:00 โ 22:00
โช
Dismantling: March 8 (Sat), 08:00 โ 18:00
โฆ
Hall B
โช
Removal: March 7 (Fri), 18:30 โ 22:00
โช
Dismantling: March 8 (Sat), 08:00 โ 18:00
โฆ
Grand Ballroom
โช
Same-Day Dismantling: March 7 (Fri), 17:00 โ 24:00
โฆ
Platz Hall, Lobby
โช
Same-Day Dismantling: March 7 (Sat), 17:00 โ 20:00
10. Important Notes
โข
The use of power tools such as compressors, welders, electric saws, electric planers, and grinders is prohibited within the exhibition hall, and painting work is limited to touch-ups only (per fire safety regulations).
โข
When installing carpet on the exhibition floor, industrial adhesive cannot be used. A special adhesive that is easy to remove, such as latex glue, must be used.
โข
If any damage occurs to the exhibition floor, walls, or other structures due to nails or adhesive, the exhibitor will be responsible for restoration costs.
โข
Do not pour or spill water on the floor, as there are electrical facilities beneath the trench covers.